The reservoir behind the famous glory-hole spillway — when the hole runs, this page's elevation says exactly why.

Water surface elevation

430.4 ft

Bureau of Reclamation, daily · daily value, Aug 30

Water in storage

1.37 million acre-feet

Bureau of Reclamation, daily · daily value, Aug 30

Share of capacity

85.8% full

against the project figure capacity figure (USBR Solano Project data)

Below full pool

9.6 ft

full pool at 440.0 ft

This month in the record

lower than 38% of the 69 Septembers on record

monthly mean storage; record low 115,031 acre-feet (1957), record high 1.49 million acre-feet (1963)

30-day trend

-1,367 af/day

storage, 2026-07-242026-08-23; over the year -57.8 af/day. Measured change, not a forecast.

Drought at the dam

none this week

US Drought Monitor at the dam's coordinates, released 2026-08-27; the feeding basin can differ.

full pool 440 ftcolumn continues below430

85.8% full

of capacity, by storage (project figure figure, USBR Solano Project data). Sedimentation slowly shrinks real capacity.

The water line is elevation (USBR project datum); the percentage is storage ÷ capacity. They are different measures — a reservoir's volume is not linear in its depth, so the line's height in this column is not the percentage.

The last 120 days

Daily water-surface elevation in feet. The axis hugs the data — it does not start at zero. Source: committed snapshot (USBR RISE, retrieved 2026-08-31).

429.9434.9439.8Apr 26Jun 25Aug 23430.9
See the numbers as a table
DateElevation (ft)
Aug 23430.86
Aug 22430.93
Aug 21430.99
Aug 20431.07
Aug 19431.15
Aug 18431.21
Aug 17431.29
Aug 16431.35
Aug 15431.41
Aug 14431.48
Aug 13431.57
Aug 12431.66
Aug 11431.73
Aug 10431.84
Aug 9431.91
Aug 8431.97
Aug 7432.04
Aug 6432.12
Aug 5432.19
Aug 4432.28
Aug 3432.36
Aug 2432.44
Aug 1432.51
Jul 31432.57
Jul 30432.65
Jul 29432.74
Jul 28432.83
Jul 27432.91
Jul 26432.98
Jul 25433.06

Most recent 30 days shown.

The whole record

Monthly mean elevation, Jul 1975 to Aug 2026. The axis spans the pools, not zero; elevations in USBR project datum. Months with fewer than 15 gaged days are dropped, and gaps in the record break the line. Source: USBR RISE, retrieved 2026-08-31.

monthly mean elevationpool reference lines
357403449Jul 1975Feb 2001Aug 2026full pool432
See the numbers as a table
MonthMean elevation (ft)Days gaged
Aug 2026431.723
Jul 2026433.831
Jun 2026436.330
May 2026438.331
Apr 2026438.830
Mar 2026439.331
Feb 2026437.628
Jan 2026436.031
Dec 2025429.431
Nov 2025428.930
Oct 2025429.331
Sep 2025430.630
Aug 2025432.531
Jul 2025434.831
Jun 2025437.330
May 2025439.231
Apr 2025440.430
Mar 2025440.831
Feb 2025441.528
Jan 2025437.031
Dec 2024433.731
Nov 2024429.230
Oct 2024428.931
Sep 2024430.530

Most recent 24 months shown; the full monthly series is in the page's API response.

Storage against capacity

Monthly mean storage in acre-feet, zero baseline. The dashed line is the project figure capacity figure (USBR Solano Project data) — sedimentation slowly shrinks real capacity. Storage can legitimately rise past a conservation-pool line when the flood pool is in use.

monthly mean storagecapacity
0879,9381.8MJan 1957Nov 1991Aug 2026capacity1.4M
See the numbers as a table
MonthMean storage (acre-feet)Days gaged
Aug 20261,397,75423
Jul 20261,435,54331
Jun 20261,481,57030
May 20261,518,69231
Apr 20261,529,47130
Mar 20261,537,28831
Feb 20261,505,78828
Jan 20261,476,08431
Dec 20251,357,48031
Nov 20251,348,62930
Oct 20251,355,46831
Sep 20251,378,02930
Aug 20251,413,00031
Jul 20251,455,39331
Jun 20251,500,27530
May 20251,536,63031
Apr 20251,558,12230
Mar 20251,566,11531
Feb 20251,579,20528
Jan 20251,495,58131
Dec 20241,434,13331
Nov 20241,353,81130
Oct 20241,348,24531
Sep 20241,377,13130

Most recent 24 months shown.

Where these numbers come from

Readings at Lake Berryessa are the measuring agencies' own: each value above names its source (USGS gage, Bureau of Reclamation daily record, Army Corps project data, or this desk's committed copy) and its observation time in the reservoir's own time zone. The capacity figure is the project figure USBR Solano Project data number; sedimentation slowly shrinks real capacity, so the vintage travels with the percent.